:It's the right time again to give you some information about the state of things in ACP. Last year we neglected the flow of information a little, and some of you got the impression that nothing was happening anymore with the FireBee.
But the opposite is true, so we want to give you an update about the things that are currently being worked on.
• Delivery of the 2nd series
We are still busy to deliver the computers of the 2nd series. With all the things that went wrong with this batch (power transformer issue, case production - the final cases were delivered to us this January etc.) the resulting huge delay also caused an incredible mess. Some pre-orderers believed they wouldn't get a device anymore; others we had to chase down with multiple mails, posts or on other channels because their personal data had changed. At any rate, the efforts are huge. We are doing the best we can though to ...
Read more
4 Comments
• Delivery of the 2nd series
We are still busy to deliver the computers of the 2nd series. With all the things that went wrong with this batch (power transformer issue, case production - the final cases were delivered to us this January etc.) the resulting huge delay also caused an incredible mess. Some pre-orderers believed they wouldn't get a device anymore; others we had to chase down with multiple mails, posts or on other channels because their personal data had changed. At any rate, the efforts are huge. We are doing the best we can though to ...